Construction Progress at Petra Sea Resort
Construction Progress Overview
Petra Sea Resort — Petra Group
Tsikhisdziri, Georgia
Block C — Structural, Interior & Facade Progress
Reinforced Concrete Structure
Main reinforced concrete works have been fully completed.
Interior Partition & Masonry Works
Partition wall installation completed from the 1st to the 23rd floors.
Block masonry works currently in progress on the 24th and 25th floors.
Facade & Openings Installation
Facade works completed from the ground floor to the 16th floor.
Aluminum window and door installation ongoing on the 17th and 18th floors.
Block B — Structural, Interior & Facade Progress
Reinforced Concrete Structure
Main reinforced concrete works have been completed.
Interior Partition Works
Partition walls finalized on the 1st–12th and 16th–20th floors.
Partition installation currently underway on the 13th, 14th, 15th, 21st, 22nd, and 23rd floors.
Facade & Openings Installation
Ground-floor facade glazing has been completed.
Aluminum window and door installation is progressing from the 1st to the 11th floors.
Block A — Foundation Works
Structural Foundations
Foundation slab reinforcement works are currently in progress.