Construction Progress at Petra Sea Resort

Construction Progress Overview

Petra Sea Resort — Petra Group

Tsikhisdziri, Georgia

Block C — Structural, Interior & Facade Progress

Reinforced Concrete Structure

Main reinforced concrete works have been fully completed.

Interior Partition & Masonry Works

  • Partition wall installation completed from the 1st to the 23rd floors.

  • Block masonry works currently in progress on the 24th and 25th floors.

Facade & Openings Installation

  • Facade works completed from the ground floor to the 16th floor.

  • Aluminum window and door installation ongoing on the 17th and 18th floors.

Block B — Structural, Interior & Facade Progress

Reinforced Concrete Structure

Main reinforced concrete works have been completed.

Interior Partition Works

  • Partition walls finalized on the 1st–12th and 16th–20th floors.

  • Partition installation currently underway on the 13th, 14th, 15th, 21st, 22nd, and 23rd floors.

Facade & Openings Installation

  • Ground-floor facade glazing has been completed.

  • Aluminum window and door installation is progressing from the 1st to the 11th floors.

Block A — Foundation Works

Structural Foundations

Foundation slab reinforcement works are currently in progress.